Odor Control & Flow Metering for 50-lot Hillside Subdivision

Wastewater Lift StationRomtec DrawingRomtec Drawing
WASTEWATER PUMP STATION PROJECT DETAILS

Development of a new 51-lot residential subdivision in southwest Washington state required a sewage lift system, because the subdivision’s sewer lines terminated approximately 100′ below the nearest gravity sewer.

Romtec Utilities provided complete pump station design and all structural, mechanical and electrical components. A Siemens Bioxide sewage odor control system and a Cummins diesel generator with sound attenuation are included in the residential sewage pumping system located on a cul-de-sac at the lowest point of the subdivision. The duplex submersible pumps are sized for 122 gpm @ 132 TDH (duty point).

THIS ROMTEC UTILITIES SYSTEM INCLUDED

  • City specified: PLC controller, SCADA system, auxiliary power & Siemens Bioxide feed system
  • Precast concrete wet well: 6’ dia. x 20’ deep, fall & confined space entry control, interior coating
  • Pump disconnect panel: with free air stand, cable hatch
  • Davit crane: Thern 5124 crane with hand winch
  • Piping & accessories: all stainless steel
  • ITT Flygt duplex submersible pumps: NP3153 HT, 18 HP
  • Level monitoring & control: Primary – MultiTrode probe; Redundant/back-up – Multitrode probe w/MTR relays
  • Precast concrete lift station valve vault: fall & confined space entry control, 4″ system, check & plug valves, discharge pressure gauge, by-pass pumping port
  • Precast concrete pump discharge flow meter vault: Siemens Mag-meter, by-pass piping & valves
  • Lift station standby generator: Cummins 60 kW w/ATS, NG fuel, sound attenuation
  • Weather shelter: post & beam open structure
  • Pump station electrical controls: UL listed
  • Pump station telemetry: radio modem, SCADA system
  • Sewage odor control system: Siemens Bioxide chemical feed system

PDF with ADDITIONAL DETAILS

PDF with DRAWING

Services included with every Romtec Utilities Pump/Lift Station

Free pump/lift station sizing, pump performance curve, design proposal, quotation
All pump/lift station engineering – structural, mechanical, electrical – coordination with site engineer(s)
Pumping system submittals – CAD drawings, design and materials specifications
Sewer/water regulatory agency coordination and submittal approval assistance
Factory assembly of complete pre-packaged lift stations (prefabricated pumping systems)
Coordinated delivery of complete pump station to project site
On-site construction advisor and pump station start-up services
Operation and Maintenance (O&M) manuals
On-site training of operation and maintenance personnel